Control systems depend on information that is objective, timely, distributed and:
AAnonymous
BAutomated
CAccurate
DAbundant
Answer & Solution
Correct answer: C. Accurate
1. A manager compares reported results against standards.
2. A wrong report leads straight to a wrong decision.
3. So the information must be accurate.
_Source: OpenStax Principles of Management, Chapter 17, Organizational Planning and Controlling._
Related questions
Firms linking planning and control through continuous improvement adopted the cycle named Firms using strategic planning showed a median five-year return on investment of:Setting a target that staff see as impossible causes those goals to lose their:For goals to motivate, research says they must be accepted, specific and:Work must pass an inspection before the next stage may begin. That go or no-go check is caA builder walks the site advising carpenters while they work. That concurrent control is cA builder inspects all materials for quality before any work starts. That is an example ofA manager notices activity drifting from the plan and acts to bring it back. That step is