A builder walks the site advising carpenters while they work. That concurrent control is called:
AStandard control
BSteering control
CStorage control
DStaffing control
Answer & Solution
Correct answer: B. Steering control
1. Work has started but is not yet finished.
2. The manager reacts to what is happening in the moment.
3. That is a steering control.
_Source: OpenStax Principles of Management, Chapter 17, Organizational Planning and Controlling._
Related questions
Firms linking planning and control through continuous improvement adopted the cycle named Control systems depend on information that is objective, timely, distributed and:Firms using strategic planning showed a median five-year return on investment of:Setting a target that staff see as impossible causes those goals to lose their:For goals to motivate, research says they must be accepted, specific and:Work must pass an inspection before the next stage may begin. That go or no-go check is caA builder inspects all materials for quality before any work starts. That is an example ofA manager notices activity drifting from the plan and acts to bring it back. That step is