A builder inspects all materials for quality before any work starts. That is an example of:
APrecontrol
BPostcontrol
CPaycontrol
DPartcontrol
Answer & Solution
Correct answer: A. Precontrol
1. Nothing has been built yet at this point.
2. The check aims to stop a problem before it can occur.
3. That is a precontrol.
_Source: OpenStax Principles of Management, Chapter 17, Organizational Planning and Controlling._
Related questions
Firms linking planning and control through continuous improvement adopted the cycle named Control systems depend on information that is objective, timely, distributed and:Firms using strategic planning showed a median five-year return on investment of:Setting a target that staff see as impossible causes those goals to lose their:For goals to motivate, research says they must be accepted, specific and:Work must pass an inspection before the next stage may begin. That go or no-go check is caA builder walks the site advising carpenters while they work. That concurrent control is cA manager notices activity drifting from the plan and acts to bring it back. That step is