If 3/5th of a cistern is filled in 1 minute, how much more time is required to fill the rest of it?Read the answer and worked solution →Pipes A and B can fill a tank in X minutes and 6 minutes respectively. Together they fill it in 1.5 minutes. Find X.Read the answer and worked solution →10 men can finish painting a wall in 8 days. How many more men are needed to finish the same work in 4 days?Read the answer and worked solution →A pipe can fill a tank in 15 hours. Due to a leak at the bottom, it takes 20 hours to fill. If the tank is full, in how much time will the leak empty it?Read the answer and worked solution →If 200 men can construct a building in 1024 days, how many men are needed to construct the same building in 256 days?Read the answer and worked solution →Trij can paint a wall alone in 7.2 days while Madhu takes 10.8 days for the same work. Working together, how many days will they take to paint 5/6 of the wall?Read the answer and worked solution →Rohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 days. In how many days can Rohit alone finish the job?Read the answer and worked solution →Complete the rule for workers and timeRead the answer and worked solution →True or false: workers and timeRead the answer and worked solution →Scaling the workforceRead the answer and worked solution →Rises or falls as the workforce grows?Read the answer and worked solution →Order the steps: a time and work questionRead the answer and worked solution →Assertion and reason: workers and timeRead the answer and worked solution →Two are true, one is notRead the answer and worked solution →Three of these are wrong. Find the one that holds.Read the answer and worked solution →Tap every situation that behaves like time and workRead the answer and worked solution →Reading a time and work setupRead the answer and worked solution →True or false: sharing a fixed jobRead the answer and worked solution →Which equation, and why?Read the answer and worked solution →Flip and pair: situation with proportionRead the answer and worked solution →Spot the odd one outRead the answer and worked solution →Complete the constant for a fixed jobRead the answer and worked solution →Scaling a workforce, harder casesRead the answer and worked solution →Does this change the total work, or only the time?Read the answer and worked solution →True or false: worker-daysRead the answer and worked solution →Order the reasoning: why more hands finish soonerRead the answer and worked solution →Assertion and reason: sharing the workRead the answer and worked solution →Complete the two-way ruleRead the answer and worked solution →Spot the one that does not belongRead the answer and worked solution →Tap every quantity that stays fixed in a time and work problemRead the answer and worked solution →

Worked practice questions

If 3/5th of a cistern is filled in 1 minute, how much more time is required to fill the rest of it?

  1. 30 sec
  2. 36 sec
  3. 40 sec
  4. 24 sec
Show answer and solution

Correct answer: C. 40 sec

1. In 1 minute (60 sec) the rate fills 3/5 of the cistern. 2. The remaining part is 1 − 3/5 = 2/5 of the cistern. 3. Time for 2/5 = (2/5) ÷ (3/5) × 60 sec = (2/3) × 60 = 40 sec. _Source: RRB Group D (RRC) PYQ, held 27-10-2013, Q.42._

Open this question →

Pipes A and B can fill a tank in X minutes and 6 minutes respectively. Together they fill it in 1.5 minutes. Find X.

  1. 1 minute
  2. 4 minutes
  3. 5 minutes
  4. 2 minutes
Show answer and solution

Correct answer: D. 2 minutes

1. Combined rate: 1/X + 1/6 = 1/1.5 = 2/3. 2. 1/X = 2/3 - 1/6 = 4/6 - 1/6 = 3/6 = 1/2. 3. So X = 2 minutes. _Source: RRB Group D CEN-02/2018 PYQ, Q.20._

Open this question →

10 men can finish painting a wall in 8 days. How many more men are needed to finish the same work in 4 days?

  1. 10
  2. 8
  3. 5
  4. 20
Show answer and solution

Correct answer: A. 10

1. Total work = 10 x 8 = 80 man-days. 2. To finish in 4 days, men needed = 80 / 4 = 20. 3. Extra men = 20 - 10 = 10. _Source: RRB Group D CEN-02/2018 PYQ, Q.63._

Open this question →

How to practise

  1. Choose a Time and Work question and try to work out your answer.
  2. Open the question to check the correct answer and read its worked solution.
  3. Continue in the app for bite-sized lessons, explanations and review with Quill. You can start without creating an account.

More Quantitative Aptitude topics