10 men can finish painting a wall in 8 days. How many more men are needed to finish the same work in 4 days?
A10
B8
C5
D20
Answer & Solution
Correct answer: A. 10
1. Total work = 10 x 8 = 80 man-days.
2. To finish in 4 days, men needed = 80 / 4 = 20.
3. Extra men = 20 - 10 = 10.
_Source: RRB Group D CEN-02/2018 PYQ, Q.63._
Keep practising Time and Work
Browse all Time and Work questions for Accenture Hiring, or explore more Quantitative Aptitude topics.
Related questions
For a fixed amount of work, the product of the number of workers and the days taken is:A can finish a job in 20 days. After working 5 days he leaves. The fraction of work left iA pipe fills a tank in 6 hours while an outlet empties it in 8 hours. With both open the tA is twice as fast as B. Working together they finish a job in 8 days. A alone would take:A and B together finish a job in 12 days. A alone takes 20 days. B alone would take:A can do a piece of work in 10 days and B in 15 days. Working together they finish it in:If 12 workers can complete a task in 8 days, 16 workers will complete it in:If 6 men finish a job in 10 days, how many days will 4 men take at the same rate?