10 men can finish painting a wall in 8 days. How many more men are needed to finish the same work in 4 days?
A10
B8
C5
D20
Answer & Solution
Correct answer: A. 10
1. Total work = 10 x 8 = 80 man-days.
2. To finish in 4 days, men needed = 80 / 4 = 20.
3. Extra men = 20 - 10 = 10.
_Source: RRB Group D CEN-02/2018 PYQ, Q.63._
Related questions
A and B together complete a work in 12 days. A alone in 18 days. How long does B alone takRohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 daA and B together finish a task in 1.5 days, but A left early and the task took 2 days in aTrij can paint a wall alone in 7.2 days while Madhu takes 10.8 days for the same work. WorIf 200 men can construct a building in 1024 days, how many men are needed to construct theTwo persons Kuldeep and Agarkar can reap a field in 8 and 12 hours respectively. They workA pipe can fill a tank in 15 hours. Due to a leak at the bottom, it takes 20 hours to fillPanu, Jiban and Jalil complete a task alone in 30, 20 and 60 days respectively. Jiban work