Rohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 days. In how many days can Rohit alone finish the job?
A25 days
B32 days
C30 days
D35 days
Answer & Solution
Correct answer: C. 30 days
1. Together one day's work = 1/10; Rohan's one day's work = 1/15.
2. Rohit's one day's work = 1/10 - 1/15 = 3/30 - 2/30 = 1/30.
3. So Rohit alone takes 30 days.
_Source: RRB Group D CEN-02/2018 PYQ, Q.46._
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15