Scaling the workforce
Exercise and reference answers
- Questions
- Question
- If 2 workers take 12 days, 4 workers take
- Choices
- 6 days
- 24 days
- 12 days
- Correct choice
- 6 days
- Question
- If 3 workers take 12 days, 6 workers take
- Choices
- 18 days
- 6 days
- 24 days
- Correct choice
- 6 days
- Question
- Halving the workforce does what to the time?
- Choices
- halves it
- leaves it alone
- doubles it
- Correct choice
- doubles it
- Question
- Workers and days for one job satisfy
- Choices
- x₁y₁ = x₂y₂
- x₁/y₁ = x₂/y₂
- x + y = k
- Correct choice
- x₁y₁ = x₂y₂
Explanation
With the job fixed, workers times days is constant
so the two scale reciprocally. Source: syllabus Maths, Ch 11 Direct and Inverse Proportions.