A project manager traces the longest chain of linked tasks in her plan, knowing a slip there delays everything. That chain is the:
ACritical path
BCentral path
CCrossing path
DClearing path
Answer & Solution
Correct answer: A. Critical path
1. Every task on it must finish on time.
2. Otherwise the whole project slips.
3. It is the critical path.
_Source: OpenStax Introduction to Business, Chapter 10, Achieving World-Class Operations Management._
Related questions
A box of cookies is produced, stored and then sold, unlike a service, because a good can bHow many parties are involved in the services marketing triangle?Giving employees autonomy to solve customer problems on the spot is called employee:The moment of contact where external promises are upheld or broken is the:Communication between the service provider and the customer is called:Which is named as a key component of that inward-facing marketing?Motivating employees to deliver customer value as a team is:Employees in a service business are described as the firm's: