A project manager traces the longest chain of linked tasks in her plan, knowing a slip there delays everything. That chain is the:

ACritical path
BCentral path
CCrossing path
DClearing path
Answer & Solution
Correct answer: A. Critical path
1. Every task on it must finish on time. 2. Otherwise the whole project slips. 3. It is the critical path. _Source: OpenStax Introduction to Business, Chapter 10, Achieving World-Class Operations Management._