A supervisor pins up a bar chart on a time line comparing planned work with actual work. This chart is named after:
AHenry Ford
BHenry Baldrige
CHenry Deming
DHenry Gantt
Answer & Solution
Correct answer: D. Henry Gantt
1. They suit projects with only a few tasks.
2. They show progress at a glance.
3. They are named after Henry Gantt.
_Source: OpenStax Introduction to Business, Chapter 10, Achieving World-Class Operations Management._
Related questions
A box of cookies is produced, stored and then sold, unlike a service, because a good can bHow many parties are involved in the services marketing triangle?Giving employees autonomy to solve customer problems on the spot is called employee:The moment of contact where external promises are upheld or broken is the:Communication between the service provider and the customer is called:Which is named as a key component of that inward-facing marketing?Motivating employees to deliver customer value as a team is:Employees in a service business are described as the firm's: