For a fixed amount of work, the product of the number of workers and the days taken is:
AAlways increasing
BConstant
CAlways decreasing
DEqual to the number of days
Answer & Solution
Correct answer: B. Constant
1. Workers and days are in inverse proportion for a fixed job.
2. If one doubles, the other halves, leaving their product untouched.
3. That constant product measures the total work, in worker-days.
4. It is why 6 men for 10 days and 4 men for 15 days both represent 60 worker-days.
5. This constant is the quantity to compute first in almost every question of this kind.
_Source: NCERT Class 8 Maths, Ch 11 'Direct and Inverse Proportions', S11.3 Inverse Proportion_
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15