If 12 workers can complete a task in 8 days, 16 workers will complete it in:

A4 days
B6 days
C9 days
D10 days
Answer & Solution
Correct answer: B. 6 days
1. The total work is 12 x 8 = 96 worker-days. 2. This total does not change when the team size changes. 3. With 16 workers the time needed is 96 / 16. 4. That is 6 days. 5. More workers means fewer days, so the answer must fall below 8, which rules out 9 and 10. _Source: NCERT Class 8 Maths, Ch 11 'Direct and Inverse Proportions', S11.3 Inverse Proportion_