If 12 workers can complete a task in 8 days, 16 workers will complete it in:
A4 days
B6 days
C9 days
D10 days
Answer & Solution
Correct answer: B. 6 days
1. The total work is 12 x 8 = 96 worker-days.
2. This total does not change when the team size changes.
3. With 16 workers the time needed is 96 / 16.
4. That is 6 days.
5. More workers means fewer days, so the answer must fall below 8, which rules out 9 and 10.
_Source: NCERT Class 8 Maths, Ch 11 'Direct and Inverse Proportions', S11.3 Inverse Proportion_
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15