If 6 men finish a job in 10 days, how many days will 4 men take at the same rate?
A15 days
B12 days
C16 days
D20 days
Answer & Solution
Correct answer: A. 15 days
1. Men and days are in inverse proportion, so their product is the total work.
2. The work here is 6 x 10 = 60 man-days.
3. With 4 men, the days needed are 60 / 4.
4. That is 15 days.
5. Fewer men must mean more days, so any answer below 10 would be wrong on inspection.
_Source: NCERT Class 8 Maths, Ch 11 'Direct and Inverse Proportions', S11.3 Inverse Proportion_
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15