As the number of workers on a job increases, the time taken to finish it:
AIncreases in the same ratio
BStays the same
CFirst rises, then falls
DDecreases
Answer & Solution
Correct answer: D. Decreases
1. Two quantities are in inverse proportion when one rises as the other falls.
2. As the number of workers increases, the time taken to finish the job decreases.
3. Doubling the workers halves the time, so the product of workers and days stays constant.
4. That constant product is the total work to be done.
5. Option A describes direct proportion, which is the opposite relationship.
_Source: syllabus Maths, Ch 11 'Direct and Inverse Proportions', S11.3 Inverse Proportion_
Keep practising Time and Work
Browse all Time and Work questions for AFCAT, or explore more Quantitative Aptitude topics.
Related questions
For a fixed amount of work, the product of the number of workers and the days taken is:A can finish a job in 20 days. After working 5 days he leaves. The fraction of work left iA pipe fills a tank in 6 hours while an outlet empties it in 8 hours. With both open the tA is twice as fast as B. Working together they finish a job in 8 days. A alone would take:A and B together finish a job in 12 days. A alone takes 20 days. B alone would take:A can do a piece of work in 10 days and B in 15 days. Working together they finish it in:If 12 workers can complete a task in 8 days, 16 workers will complete it in:If 6 men finish a job in 10 days, how many days will 4 men take at the same rate?