A promisee accepts late performance. To claim delay compensation he must have?
APaid an extra deposit
BWaited a full year
CGot prior court sanction
DGiven notice at acceptance
Answer & Solution
Correct answer: D. Given notice at acceptance
Accepting late performance forfeits delay compensation unless notice of the intention to claim is given at acceptance.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?