A promisee accepts late performance. To claim delay compensation he must have?

APaid an extra deposit
BWaited a full year
CGot prior court sanction
DGiven notice at acceptance
Answer & Solution
Correct answer: D. Given notice at acceptance
Accepting late performance forfeits delay compensation unless notice of the intention to claim is given at acceptance.