Liquidated damages are an amount that the parties fix when?
AOn a termination notice
BWhen forming the contract
CAfter the breach occurs
DAt the court hearing
Answer & Solution
Correct answer: B. When forming the contract
The parties designate the sum in advance, during the formation of the contract.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?Which circumstance generally defeats specific performance?