A contractor quits a school job midway. For work done, he claims on what basis?
ALiquidated damages
BSpecific performance
CAn injunction order
DA quantum meruit claim
Answer & Solution
Correct answer: D. A quantum meruit claim
He is paid the reasonable value of services already rendered, which is quantum meruit.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?Which circumstance generally defeats specific performance?