A liquidated sum must approximate likely loss assessed when?

AWhen the breach occurs
BWhen the contract is made
CWhen suit is filed
DWhen judgment is given
Answer & Solution
Correct answer: B. When the contract is made
The estimate is judged as of the date the agreement was entered into, not afterwards.