A liquidated sum must approximate likely loss assessed when?
AWhen the breach occurs
BWhen the contract is made
CWhen suit is filed
DWhen judgment is given
Answer & Solution
Correct answer: B. When the contract is made
The estimate is judged as of the date the agreement was entered into, not afterwards.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?Which circumstance generally defeats specific performance?