A bond at 12% interest raises it to 75% on default. B recovers?
AThe entire 75% interest rate
BReasonable compensation
CJust the original 12% rate
DNothing beyond the principal
Answer & Solution
Correct answer: B. Reasonable compensation
The 75% rate is a penalty, so the Court allows only reasonable compensation rather than the stipulated rate.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?