A buys 1,000 tons of iron from C at Rs 80 to resell to B at Rs 100, telling C so. C defaults; no other iron exists. C owes A?
ARs 1,80,000
BRs 80,000
CRs 20,000
DRs 1,00,000
Answer & Solution
Correct answer: C. Rs 20,000
A lost a margin of Rs 20 on each of 1,000 tons, and C knew the purpose, so Rs 20,000 is payable.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?