Start learning →

Price 12,000 and revised total cost 15,000. Expected total loss?

A3,600
B1,500
C2,400
D3,000
Answer & Solution
Correct answer: D. 3,000
Expected cost of 15,000 less the contract price of 12,000 leaves a loss of 3,000, to be booked in full at once.
Practise this question with Quill — CA Inter →

Keep practising Construction Contracts (AS 7)

Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.

Start a Construction Contracts (AS 7) lesson →