Percentage of completion is an exception to which basic principle?

AThe entity concept
BThe going concern concept
CThe realisation principle
DThe dual aspect concept
Answer & Solution
Correct answer: C. The realisation principle
Revenue is booked as work progresses, before the contract is delivered, which departs from the realisation principle.