Costs incurred plus recognised profits are reduced by which items?
AUnrecognised profits and overheads
BEstimated future costs and taxes
CRetention money and snagging costs
DRecognised losses and progress billings
Answer & Solution
Correct answer: D. Recognised losses and progress billings
The net amount due from or to customers is costs plus recognised profits less recognised losses and progress billings.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?On the balance sheet, excess of costs over billings is shown as what?