A lump sum and scheduled contract suits when what is true?
AItems are few or quantities known
BQuantities cannot be estimated
CWork is urgent and unplanned
DThe owner wants cost reimbursed
Answer & Solution
Correct answer: A. Items are few or quantities known
It works when the number of items is limited or exact quantities of work can be worked out in advance.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?On the balance sheet, excess of costs over billings is shown as what?