Excess of billings over costs on uncompleted contracts appears where?

AUnder fixed assets
BUnder current liabilities
CUnder equity reserves
DUnder current assets
Answer & Solution
Correct answer: B. Under current liabilities
Progress billings beyond costs incurred mean the firm owes work, so the amount is a current liability.