Cost to date is 5,500 and revised total cost is 11,000. Percent complete?
A60%
B55%
C40%
D50%
Answer & Solution
Correct answer: D. 50%
Cost to date divided by revised total cost is 5,500 / 11,000, which equals 50%.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?