Under the completed-contract method, when are revenues recognised?

AWhen each progress bill is raised
BAfter the project is fully completed
CIn proportion to costs each year
DAt the date of contract signing
Answer & Solution
Correct answer: B. After the project is fully completed
Revenue, cost and gross profit are held back until the project is fully finished.