Cost plus percentage contracts suit which kind of work?

AWork with complete specifications
BEmergency work, e.g. poor foundations
CSmall jobs with exact quantities
DRoutine work with fixed drawings
Answer & Solution
Correct answer: B. Emergency work, e.g. poor foundations
Drawings and specifications are not needed at signing, which suits emergency work or difficult foundation conditions.