Which is not a main contract type by payment mechanism?

ARe-measurement contract
BFixed lump sum contract
CCost-reimbursable contract
DSubcontract agreement
Answer & Solution
Correct answer: D. Subcontract agreement
The three main types are lump sum, re-measurement and cost-reimbursable; a subcontract agreement is a different kind of contract between builder and specialist.