Which is not a main contract type by payment mechanism?
ARe-measurement contract
BFixed lump sum contract
CCost-reimbursable contract
DSubcontract agreement
Answer & Solution
Correct answer: D. Subcontract agreement
The three main types are lump sum, re-measurement and cost-reimbursable; a subcontract agreement is a different kind of contract between builder and specialist.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?