In a re-measurement contract, how is the price fixed?

AMeasured work at scheduled prices
BActual cost plus a negotiated fee
CA single agreed lump sum for the job
DA percentage added to documented cost
Answer & Solution
Correct answer: A. Measured work at scheduled prices
The work done is measured in detail and valued with reference to a schedule of prices in the contract.