A unit cost contract is priced on what basis?
AOne single price for the whole job
BA percentage over lowest tender
CActual cost plus a fixed fee
DUnits put in place at a rate each
Answer & Solution
Correct answer: D. Units put in place at a rate each
Payment is calculated by multiplying a specific rate for each item by the quantity actually put in place.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?