Sectional completion allows a construction contract to have what?

AOnly one final completion date
BSeparate dates for each section
CCompletion before the tender
DPayment only after handover
Answer & Solution
Correct answer: B. Separate dates for each section
Larger staged projects set different completion dates for different parts, so the client can occupy finished sections early.