Which event starts the defects rectification period in a construction contract?
APractical completion
BFixing the base date
CSigning the tender
DIssue of the tender
Answer & Solution
Correct answer: A. Practical completion
Once practical completion is certified, the owner has accepted the work and the defects rectification period begins.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?