What is a retention in a construction contract?

AA bonus paid for early completion
BMoney withheld by the owner as security
CA penalty charged for late work
DA deposit paid by the contractor
Answer & Solution
Correct answer: B. Money withheld by the owner as security
The owner holds back part of the payment as security against incomplete or defective works.