What is a retention in a construction contract?
AA bonus paid for early completion
BMoney withheld by the owner as security
CA penalty charged for late work
DA deposit paid by the contractor
Answer & Solution
Correct answer: B. Money withheld by the owner as security
The owner holds back part of the payment as security against incomplete or defective works.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?