In a cost plus fixed fee contract, what is paid above documented cost?

AAn agreed negotiated fee
BNothing beyond the cost
CA share of final savings
DA percentage of cost
Answer & Solution
Correct answer: A. An agreed negotiated fee
The owner reimburses documented cost and adds a negotiated fee that covers overhead and profit.