In a cost plus fixed fee contract, what is paid above documented cost?
AAn agreed negotiated fee
BNothing beyond the cost
CA share of final savings
DA percentage of cost
Answer & Solution
Correct answer: A. An agreed negotiated fee
The owner reimburses documented cost and adds a negotiated fee that covers overhead and profit.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?