Which contract fixes one sum for all the work, with no cost breakdown?
AUnit cost contract
BLump sum contract
CRemeasurement contract
DCost plus contract
Answer & Solution
Correct answer: B. Lump sum contract
A lump sum contract promises a specified total for completed work, so the owner sees no breakdown of cost.
Keep practising Construction Contracts (AS 7)
Browse all Construction Contracts (AS 7) questions for CA Inter, or explore more Accounting topics.
Related questions
What does a guaranteed maximum price provide in a cost-plus contract?Unit cost contracts are often used for which type of construction?A lump sum and scheduled contract suits when what is true?Percentage of completion is an exception to which basic principle?Completion of production basis recognises revenue before sale for:Costs incurred plus recognised profits are reduced by which items?IAS 11 shows gross amount due from customers for contract work as:Excess of billings over costs on uncompleted contracts appears where?