A breach that occurs before the time fixed for performance has arrived is called:
AAnticipatory breach
BNominal breach
CActual breach
DConstructive discharge
Answer & Solution
Correct answer: A. Anticipatory breach
Anticipatory breach (Section 39) is repudiation by the promisor before the due date of performance.
Keep practising Breach of Contract and its Remedies
Browse all Breach of Contract and its Remedies questions for CA Foundation, or explore more Businesslaw topics.
Related questions
A contractor quits a school job midway. For work done, he claims on what basis?A liquidated sum must approximate likely loss assessed when?At common law a liquidated damages clause fails when its purpose is to do what?Damages that are uncertain or depend on contingencies are called what?Liquidated damages are an amount that the parties fix when?Which remedy can bar an employee from working for a rival when specific performance fails?At common law, a claimant's rights were limited to what?Specific performance is generally unavailable for shares that are what?