A breach that occurs before the time fixed for performance has arrived is called:
AAnticipatory breach
BNominal breach
CActual breach
DConstructive discharge
Answer & Solution
Correct answer: A. Anticipatory breach
Anticipatory breach (Section 39) is repudiation by the promisor before the due date of performance.
Related questions
A agrees to sell rice to B for delivery in two months; on the due date the market price haTo the rule that compensation cannot exceed the stipulated sum, an exception exists where Under Section 75, a party who rightfully rescinds a contract is:A court order restraining a party from doing what he promised not to do (e.g. a singer perWhere damages are not an adequate remedy, the court may order the defaulting party to actuA claim on quantum meruit is available only if:The remedy of 'quantum meruit' means a claim for:A stipulated sum that is a genuine pre-estimate of the likely loss on breach is best descr