What happens if a task lying on the critical path is not completed on time?
AOnly that single task is recorded as late
BThe entire project will fall behind schedule
CThe project finishes earlier than planned
DThe task is simply removed from the network
Answer & Solution
Correct answer: B. The entire project will fall behind schedule
1. The critical path is the longest path through the linked activities.
2. Being longest, it has no spare time built into it anywhere.
3. A delay to any task on it therefore pushes every following task on that path back by the same amount.
4. Since the path already determines the finish date, the entire project falls behind schedule.
5. Tasks off the critical path are different, because they can be delayed a bit or done early without harming the finish date.
6. That contrast is the whole point of identifying the critical path in the first place, which is why option A misses the significance of the delay.
_Source: OpenStax Introduction to Business (CC BY 4.0), Ch 10 "Achieving World-Class Operations Management", section The Big Picture: Critical Path Method and PERT_
Related questions
What is business process management described as being able to do for a company?How have banks used automation to make services more accessible to customers?How do retail stores use point-of-sale terminals to improve operations?What does computer-integrated manufacturing combine?A flexible manufacturing system is expensive to install. Which combination of advantages jWhat does a flexible manufacturing system blend into an integrated system?For which kinds of task is replacing human effort with robots most effective?What is a robot in a production setting?