In a critical path method network, what is the critical path?
AThe cheapest route through the linked activities
BThe route using the fewest workers on the project
CThe route with the fewest separate activities on it
DThe longest path through the linked activities
Answer & Solution
Correct answer: D. The longest path through the linked activities
1. A critical path method diagram links activities with arrows showing dependence.
2. Several different paths run through the network from start to finish.
3. The longest of those paths is called the critical path, because it is what limits the finish date.
_Source: OpenStax Introduction to Business (CC BY 4.0), Ch 10 "Achieving World-Class Operations Management", section The Big Picture: Critical Path Method and PERT_
Related questions
What is business process management described as being able to do for a company?How have banks used automation to make services more accessible to customers?How do retail stores use point-of-sale terminals to improve operations?What does computer-integrated manufacturing combine?A flexible manufacturing system is expensive to install. Which combination of advantages jWhat does a flexible manufacturing system blend into an integrated system?For which kinds of task is replacing human effort with robots most effective?What is a robot in a production setting?