What does a manager do first when applying the critical path method to a project?

AAssign three time estimates to each of the activities
BPlot each activity as a bar against a calendar line
CIdentify the activities, their relationships, and their order
DOrder all the materials the project is going to require
Answer & Solution
Correct answer: C. Identify the activities, their relationships, and their order
1. In the critical path method the manager identifies all the activities required to complete the project. 2. The relationships between those activities are identified next. 3. The order in which they must be completed follows from those relationships. 4. Only then does the manager draw a diagram using arrows to show how the tasks depend on each other. _Source: OpenStax Introduction to Business (CC BY 4.0), Ch 10 "Achieving World-Class Operations Management", section The Big Picture: Critical Path Method and PERT_