Specifying and controlling the time required for each step in production is known as what?

ARouting of the production work
BPurchasing of the raw materials
CScheduling of the production work
DForecasting of the future demand
Answer & Solution
Correct answer: C. Scheduling of the production work
1. Scheduling is closely related to routing but answers a different question. 2. Routing asks where the work goes next, while scheduling asks when each step happens. 3. The operations manager prepares timetables showing the most efficient sequence and then ensures the necessary materials and labor are in the right place at the right time. _Source: OpenStax Introduction to Business (CC BY 4.0), Ch 10 "Achieving World-Class Operations Management", section Scheduling: When Do We Do It?_