Home › B.Tech Civil › civilengineering › Concreting Equipment › Refrigeration plant capacity for pre-cooling of …
Refrigeration plant capacity for pre-cooling of mass concrete is expressed in tons of refrigeration. One ton of refrigeration is equivalent to:
Answer & Solution
Correct answer: A.
1. The unit's sizing formula Eq. 7.1 divides heat to be removed (Btu/hr) by 12000 Btu/hr.
2. That divisor converts the heat-removal duty into refrigeration tons.
3. So one ton of refrigeration is taken as 12000 Btu/hr in the formula.
4. The maximum concrete placing rate (cyd/hr) multiplied by heat-to-be-removed (Btu/cyd) gives total Btu/hr.
5. The other Btu/hr values misstate the standard one-ton equivalent.
_Source: IGNOU Concrete Technology, Unit 7 "Concreting Equipment" (Mixers, Cableways, Batchers, Buckets, Pre/Post Cooling)._
Related questions
In the heat-balance equation, the specific heat of cement is generally taken between:In the heat-balance equation Eq. 7.2 for ice quantity, the latent heat of fusion of ice isIn the post-cooling pumping plant, each pipe coil is supplied at a flow rate of approximatThe unit specifies that individual embedded pipe runs may range from 180 to 360 m, with a Embedded post-cooling pipes carry circulating cool water through hardened concrete. The unCement is normally batched dry. To avoid moisture condensation that would adversely affectVacuum cooling of aggregates uses the lower boiling point of water at sub-atmospheric presCoarse aggregate is cooled by inundation in a tank of chilled water. With water at 2 °C, e