The unit specifies that individual embedded pipe runs may range from 180 to 360 m, with a target design length of approximately:
Answer & Solution
Correct answer: A.
1. Pipe runs in a post-cooling system are sized to balance flow resistance with cooling effect.
2. The unit gives a permitted range of 180 to 360 m for an individual pipe run.
3. The recommended target length for design purposes is 240 m, sitting near the middle of the range.
4. Pipe loops on the same manifold are kept roughly equal so flow and cooling are balanced.
5. 60 m and 500 m fall outside the recommended range.
_Source: IGNOU Concrete Technology, Unit 7 "Concreting Equipment" (Mixers, Cableways, Batchers, Buckets, Pre/Post Cooling)._
Related questions
Refrigeration plant capacity for pre-cooling of mass concrete is expressed in tons of refrIn the heat-balance equation, the specific heat of cement is generally taken between:In the heat-balance equation Eq. 7.2 for ice quantity, the latent heat of fusion of ice isIn the post-cooling pumping plant, each pipe coil is supplied at a flow rate of approximatEmbedded post-cooling pipes carry circulating cool water through hardened concrete. The unCement is normally batched dry. To avoid moisture condensation that would adversely affectVacuum cooling of aggregates uses the lower boiling point of water at sub-atmospheric presCoarse aggregate is cooled by inundation in a tank of chilled water. With water at 2 °C, e