For cycle-time calculations the unit lists suggested cableway speeds. The carriage travel speed is taken as approximately:
A76 m/min
B91 m/min
C180 m/min
D305 m/min
Answer & Solution
Correct answer: D. 305 m/min
1. The unit lists four speeds used for cycle-time estimation.
2. Load hoisting is taken as 76 m/min and load lowering as 91 m/min.
3. Carriage travel along the suspension cable is taken as 305 m/min.
4. Tail mast travel for radial cableways with moving tail mast is taken as 8 m/min.
5. The hoist and lower values are slower because they handle the load directly.
_Source: IGNOU Concrete Technology, Unit 7 "Concreting Equipment" (Mixers, Cableways, Batchers, Buckets, Pre/Post Cooling)._
Keep practising Concreting Equipment
Browse all Concreting Equipment questions for B.Tech Civil, or explore more Civil Engineering topics.
Related questions
Refrigeration plant capacity for pre-cooling of mass concrete is expressed in tons of refrIn the heat-balance equation, the specific heat of cement is generally taken between:In the heat-balance equation Eq. 7.2 for ice quantity, the latent heat of fusion of ice isIn the post-cooling pumping plant, each pipe coil is supplied at a flow rate of approximatThe unit specifies that individual embedded pipe runs may range from 180 to 360 m, with a Liquid nitrogen is used as an alternate cooling agent. The unit gives its boiling temperatEnergy imparted to a batch during mixing converts to heat in the concrete. The unit estimaIn a radial-travelling cableway, two backstays are required at the stationary tower whenev