For cycle-time calculations the unit lists suggested cableway speeds. The carriage travel speed is taken as approximately:

A76 m/min
B91 m/min
C180 m/min
D305 m/min
Answer & Solution
Correct answer: D. 305 m/min
1. The unit lists four speeds used for cycle-time estimation. 2. Load hoisting is taken as 76 m/min and load lowering as 91 m/min. 3. Carriage travel along the suspension cable is taken as 305 m/min. 4. Tail mast travel for radial cableways with moving tail mast is taken as 8 m/min. 5. The hoist and lower values are slower because they handle the load directly. _Source: IGNOU Concrete Technology, Unit 7 "Concreting Equipment" (Mixers, Cableways, Batchers, Buckets, Pre/Post Cooling)._