A process loss that is inherent in the nature of the work and can be anticipated is called
Anormal loss
Babnormal loss
Cabnormal gain
Dinter process loss
Answer & Solution
Correct answer: A. normal loss
1. Process losses are of two kinds.
2. Normal process loss, also called normal wastage, is inherent in the nature of the work.
3. It can be reasonably anticipated from the material, the operation and past technical data.
4. It is unavoidable, which is exactly why its cost is absorbed by the good units.
_Source: ICAI Cost and Management Accounting Ch10 'Process and Operation Costing', section 10.3_
Related questions
Work in Process for a department opens at $102,896 and takes in $599,427 of materials, $58Eight one gallon buckets are left outside in the rain and each ends up three quarters fullMaterials cost $13.41 per unit started and conversion costs $20.40 per equivalent unit. WhUnits carried in from April and finished in May cost $199,184 in total, and units started Ending work in process is 7,300 units, 30% complete, with materials at $13.41 per unit andBeginning work in process cost $17.44 per unit and was 20% complete, and conversion costs Materials costing $599,427 were added in May for the 44,700 units started that month. WhatDirect labor of $589,323 and factory overhead of $314,601 are incurred in May against 44,3