A is 50% more efficient than B. If B takes 30 days to complete a task alone, how many days does A take alone?
A$45$ days
B$20$ days
C$15$ days
D$25$ days
Answer & Solution
Correct answer: B. $20$ days
50% more efficient means A's rate = 1.5 × B's rate. If B's time = 30 days, A's time = 30/1.5 = 20 days. The trap '50% less time = 15 days' confuses rate and time.
Related questions
Those two workers, at that combined rate, finish the whole job in:A worker finishing in 5 hours and another in 20 hours together do what share of the job eaConverting two fifths of an hour into minutes gives:In work problems, the parts of the job done by each worker in one hour add up to:Flying into that same 30 mph wind, the same plane's ground speed would be:A plane's ground speed with a tailwind of 30 mph, if the plane itself flies at 150 mph, isOn that drive, Tony's interstate speed was:Tony drives 4 hours in all, 208 miles on the interstate and 40 on country roads, going 15