20 workers can complete a project in 25 days. How long would 25 workers take to complete the same project?
A$30$ days
B$22$ days
C$20$ days
D$18$ days
Answer & Solution
Correct answer: C. $20$ days
Man-days constant: 20 × 25 = 500. With 25 workers: 500 / 25 = 20 days.
Keep practising Time and Work
Browse all Time and Work questions for CAT, or explore more Quantitative Reasoning topics.
Related questions
A is 50% more efficient than B. If B takes 30 days to complete a task alone, how many daysA pipe fills a tank in 4 hours. Due to a leak, it now takes 6 hours. The leak alone would A is twice as efficient as B. B alone finishes a job in 18 days. How long do A and B togetTwo pipes A and B fill a tank in 4 and 6 hours. A drain C empties it in 12 hours. With allA, B, C complete jobs alone in 10, 12, 15 days. Working together, they finish in:A finishes a job in 6 days, B in 4 days. Using the LCM trick (work = 12 units), what is B'A can do a job in 8 days, B in 12 days. How long do A and B take working together?