A can do a job in 8 days, B in 12 days. How long do A and B take working together?
A$10$ days
B$6$ days
C$4.8$ days
D$3.6$ days
Answer & Solution
Correct answer: C. $4.8$ days
Combined rate = 1/8 + 1/12 = 3/24 + 2/24 = 5/24. Time = 24/5 = 4.8 days. Shortcut: AB/(A+B) = 96/20 = 4.8.
Related questions
A and B together complete a work in 12 days. A alone in 18 days. How long does B alone takRohan and Rohit together can finish a job in 10 days, while Rohan alone can do it in 15 daA and B together finish a task in 1.5 days, but A left early and the task took 2 days in aTrij can paint a wall alone in 7.2 days while Madhu takes 10.8 days for the same work. WorIf 200 men can construct a building in 1024 days, how many men are needed to construct theTwo persons Kuldeep and Agarkar can reap a field in 8 and 12 hours respectively. They workA pipe can fill a tank in 15 hours. Due to a leak at the bottom, it takes 20 hours to fill10 men can finish painting a wall in 8 days. How many more men are needed to finish the sa