Three workers complete a job in 6 days. With a fourth worker of the same efficiency, the time taken is

A4 days
B4.5 days
C5 days
D5.5 days
Answer & Solution
Correct answer: B. 4.5 days
Total work = 3 x 6 = 18 worker-days. With 4 workers, 18 / 4 = 4.5 days.