Three workers complete a job in 6 days. With a fourth worker of the same efficiency, the time taken is
A4 days
B4.5 days
C5 days
D5.5 days
Answer & Solution
Correct answer: B. 4.5 days
Total work = 3 x 6 = 18 worker-days.
With 4 workers, 18 / 4 = 4.5 days.
Keep practising Clat Ug Topup
Browse all Clat Ug Topup questions for CLAT, or explore more Law topics.
Related questions
The area of a triangle with base 10 cm and height 8 cm isSimplify: (3/4) divided by (9/16) equalsFind the next number in the sequence: 2, 6, 12, 20, 30, ____Pick the option that BEST completes the analogy: Page : Book :: ____ : SymphonyArticle 15(4) of the ConstitutionUnder Article 14, a legislative classification is valid ifIdentify the part of speech of 'leaking' in: 'a leaking roof'.Choose the BEST synonym of 'meagre' in: 'The ragpickers' meagre earnings barely cover thei