Which pair is often called prime cost in costing?
ARent and depreciation cost
BDirect labor and overhead
CMaterial and overhead cost
DDirect material and labor
Answer & Solution
Correct answer: D. Direct material and labor
Prime cost covers the two direct inputs, materials and labor, that go into the product.
Keep practising Production And Cost
Browse all Production And Cost questions for CA Foundation, or explore more Business Economics topics.
Related questions
The marginal cost curve always passes through the minimum points of which two curves?What is the typical shape of the average variable cost curve?Machines and land bought for a factory are generally classed as which cost in the short ruA mill pays a monthly lease whatever it produces. Over the lease period, this payment is wFixed cost is 500. Producing 5 units costs 700 in total and 6 units costs 760. What is theA firm has TFC of 900 and AVC of 15 at 60 units. What is its total cost?At 40 units, TFC is 1,200 and TVC is 800. What is AC at 40 units?TVC is 600 for 50 units. What is the average variable cost?