Under Section 46, where no time is specified and no application is to be made, the promise must be performed:
AWithin a reasonable time
BImmediately on the date of contract
CWithin thirty days
DOnly when the promisee applies
Answer & Solution
Correct answer: A. Within a reasonable time
Where no time is fixed and no application is required, the engagement must be performed within a reasonable time, judged on the facts.
Related questions
Under Section 45, where a promise is made to two or more promisees jointly, the right to cUnder Section 50, performance of a promise may be made in the manner or at the time which:A and B agree A will deliver goods to be paid for on delivery. A need not deliver unless BActual breach of a contract can be committed:Under Section 56, where the promisor alone knew, or with reasonable diligence should have Where a contract becomes impossible or unlawful to perform after it is made, due to an unfAn agreement to do an act impossible in itself (initial impossibility) under Section 56 isUnder Section 55, where time is NOT of the essence and performance is delayed, the promise